VMRDA units Could 2026 deadline for seven street tasks linking Vizag to Bhogapuram airport


Work on the seven roads venture is in numerous levels of progress. VMRDA is endeavor this venture to supply hassle-free street connectivity to the ASR Greenfield Worldwide Airport in Bhogapuram close to Visakhapatnam. Picture: Particular Association

With the authorities gearing up for the ‘validation flight’ on the Greenfield Worldwide Airport at Bhogapuram in December to check and certify airport strategy and departure procedures for plane, the Visakhapatnam Metropolitan Area Improvement Authority (VMRDA) has set a brand new deadline of Could 2026 to finish the seven grasp plan street tasks.

The seven-road venture spanning 26.72 km requires coordination between the GVMC, Roads & Buildings, Panchayat Raj, Forests, and personal landowners who’ve parted their stretches for the tasks.

In keeping with sources, the street tasks have slowed down because of land acquisition challenges, with the hardest hurdle being the acquisition of 75 acres.

Compensation choices embrace money funds, different websites, and transferable growth rights (TDRs). To this point, only some landowners have agreed to the compensation by way of TDRs.

The seven roads are being constructed at an estimated price of Rs. 156 crore, together with CSR funds from the company firms. These roads embrace: An 8 km street from Adivivaram BRTS junction to Gandigundam (Rs. 40 crore), awaiting forest clearance; a 2.2 km street from Anandapuram NH to Gambhiram Reservoir, a 1.7 km growth from Shivashakti Nagar to the VUDA Haritha venture (Rs. 7.65 crore); a 1.4 km growth from Paradeshipalem to Gambhiram (Rs. 5.04 crore); a 3.83 km street from Nerallavalasa to Tallavalasa (Rs. 24 crore); a 3 km widening from Boyapalem Junction to Kapuluppada (Rs. 15 crore); widening of 6.32-km street from Chippada to Polipilli (Rs. 37.92 crore).

These roads are designed to ease visitors on the nationwide freeway and supply faster entry for passengers from Visakhapatnam, Vizianagaram, and Srikakulam districts to the brand new airport.

Additional, plans are afoot to widen 15 inner roads for higher connectivity at an estimated price of Rs. 390 crores. A proposed six-lane seashore hall connecting Seashore Street in Visakhapatnam to the airport is below growth, with the Detailed Challenge Report (DPR) finalised.

4 elevated corridors have additionally been proposed, linking the Aganampudi-Lankelapalem space to Kommadi.

In keeping with the knowledge out there with the VMRDA officers, non-public land have to be acquired from 348 homeowners, who might be issued transferable growth rights (TDR) bonds as compensation.

“To this point, we have now issued 155 TDRs out of 348. We’ll clear the remainder quickly. Solely vegetation clearance and preliminary basis work have been accomplished. Not one of the street widenings is prepared. Permission from the Forest Division is required for the patches in the course of some roads. Nonetheless, we’re heading in the right direction to finish the work inside the deadline,” mentioned a VMRDA official.

Talking toThe Hindu, VMRDA Chairman MV Pranav Gopal mentioned, “Regardless of the challenges, we’re decided to finish these seven roads connecting Visakhapatnam and Bhogapuram airport earlier than the home operations start. We now have set a deadline of Could 2026 to finish the works.”

However, sources mentioned that the airport’s progress is forward of schedule, with 90% of the core constructing works accomplished. Round 97% of the runway works have been completed and 92% of the taxiways works have been accomplished. The ‘validation flight’ is scheduled for December, they mentioned.

What’s validation flight?

A ‘validation flight’ is crucial for testing and certifying airport strategy and departure procedures for plane. It’s basically a check flight to make sure that the touchdown and departure procedures, infrastructure readiness, and navigational and communication programs for the brand new runway and airport adjust to regulatory and security requirements.