Chief Minister A. Revanth Reddy has set December 9 2027, because the deadline for completetion and fee of the srisailam left financial institution canal challenge. Irrigation minister n uttam kumar reddy was additionally offered.
Chief Minister A. Revanth Reddy has set December 9 2027, because the deadline for completetion and commissioning of the srisailam left financial institution canal challenge directing officers
The Chief Minister was wished the officers to skilled the work as Slbc was of essential not solely to nalgonda district however for the entrege state. The challenge supplied scope for offering water to the targetted districts with out spending cash.
Officers Involved was instruined to supply data Pertaining to Issues Encounter within the Mission Between Srisailam and Akkampalli Reservoirs. Reviewing this system of the challenge with Senior Officers on Thursday, He Mentioned choices and options associated to expertious completes of the challenge could be taken in a single Assembly that WLD BE CONVED SOON
Focus within the meantime ought to be on acquiring forest clearances. “The challenge ought to be commissioned on December 9, 2027,” He mentioned asserting that the federal government was ready to supply funds required for Slbc Works in Inexperienced Channel.
He directed the contract company jp associates to be equipped for the challenge and preserve their equipment prepared. “I cannot settle for even a day’s delay within the challenge,” He Informed the company suggesting that the company and the officers is anxious grinds make the most of the companies of consultants from in tunneling works.
Steps ought to be taken to make sure an uninterrupted energy provide to the works, and there shouldn’t be any Hindrans to the works.
Newly Appointed Authorities Advisor Lt Gen Harpal Singh, Who Assume Cost Yesterday, Participated within the assembly. Excavation is to proceed at 175 metres per thirty days from each ends, with a each day goal of set Technical Consultants mentioned the remaiing geological circumstances have been favorable, with bolt helps required solely 15–20 metres behind the excavation face.
Irrigation minister n. Uttam Kumar Reddy Knowledgeable that a sophisticated heli-borne surwey could be carried out by the nationwide geophysical analysis institute (ngri) Formations, and fault strains alongside the stay alignment.
Lt gen harpal singh pressured that air flow, redundant techniques, and documentation of methodology was important for deep tunnelling works. He additionally insisted on coaching younger engineers to construct capability inside the state.
Officers reported that tunnelling has alredy progressed 21 km from from one finish and 14 km from the opposite, with the steadiness stretch requiring extra intensive oversight. It was resolved that works could be carried out in three regulated shifts, because it takes close to 90 minutes 90 minutes to succeed in the excavation face. Additional, Junior Engineers could be deployed on each shift, mainTaining written information of each day progress.
(EOM)